The work itself, hospitals, schools, garages and shops we helped stand up

  1. mark3B-03 benchProjects checked

    A school gym frame in six working days: the sequence

    Six working days, one crane, and a southern New Hampshire school gym: the shake-out, the pick sequence, and the check values written on the back of a plan.

    6 min read

    A steel gymnasium frame under construction with a crane lifting a beam against a blue New England sky.
  2. mark3B-02 benchProjects checked

    Steel over a corridor that stayed open: how the picks were sequenced

    A school wing addition picked over a corridor that never closed: the pick radii, the flag line and the hour-by-hour window plan, read off the rigging sheet.

    6 min read

    A steel beam being lifted by a crane next to an occupied brick institutional building.
  3. mark3B-01 benchProjects checked

    Stairs and rails for a town library: the measure that decides everything

    A finish-metal note from the shop: the field measure, the 42 in guard height, the 4 in sphere, and the one dimension on a library stair that had to be cut twice.

    6 min read